Renovated pool behind frameless glass fencing, overlooking the water.

Why is cost plus the best arrangement when there are genuine unknowns

Demolition Stats

0m2

Square metres of interior pool stripped by our team

0%

of pools landed within 15% of our cost plus estimate

0%

Of pools cost less than 15% of our estimate

0%

Of pools cost more than our 15% estimate.

BeforeAfter
Pool with its surrounds dug out and a mini excavator on the lawn.
Half-empty pool with its old surrounds, before demolition.

Using cost-plus demolition, owners choose to pay for the time and disposal their pool's strip-out actually takes.

Demolition is often charged at cost plus because it's hard to tell how easily an old pool surface will come off until work starts. The owner pays agreed rates for the time it takes. This means they achieve the best value possible.

Take three 8 x 4 m pools with about 60 m² of interior each, stripped by a 3-person crew. Each pool takes 3 days.

With waste and tool fees, it could cost $9000 per pool. Two pools take the expected amount of time. Now imagine the third pool has been renovated 3 times where the interior has not been stripped. This is completely unforeseeable until demolition begins.

Now there is roughly 100% more work to complete, removing the other layers.

If a contractor charged the correct fee for the first two pools, and lost $9000 on the third pool, the total cost for a removal is $36,000, yet they have only charged $27,000.

This would be a fast way to go out of business for any contractor.

How is this risk managed?

In a fixed-price scenario, a contractor has to build in risk for the jobs that don't go as planned. This means that the jobs that do well, pay for that risk. It's worth noting as well that if a pool demolition goes quicker than expected, the contractor wins on time.

Neither option is good for the client.

In comes cost plus

Cost Plus can seem risky to the client due to the idea of an untrustworthy contractor using it to their advantage and overcharging for the product or service they have supplied.

If you're working with a reputable contractor with a good reputation in your community, you can be guaranteed that, if there are genuine unknown components of your job, you will get the best value for money using a cost-plus agreement.

Neither party carries risk, and the job is executed at its actual value without padding or over charging. A cost-plus arrangement will always involve diligent record-keeping and an agreement for both parties on the amount of time and costs prior to the final charges being agreed upon.



Stripping the old pool interior with a jackhammer.
Demolition saw cutting through the top of the pool wall.
Chipping old mosaic tiles off the pool wall with a chisel.